Builderprise provided overall construction works for 2 nos. of fire station substructure and
superstructur. DfMA is applied on ground floor to 2nd floor and construction method
changes to traditional method due to limitation of lifting appliances in Airport Height
Restricted Area. Narrow site area is another challenge for site logistic as super tight
program requirements