Tseung Kwan Desalination Plant – Installation of DfMA Precast Footbridge
Nov 23 to Aug 24
AA-JEC-China State Joint Venture
Third Runway Concourse and Apron Works - Rebar Fixing Works Transferred from 3405 to 3408
13/WSD/17
Builderprise provided overall construction and professional engineering support services
for 7nos. of precast irregular shape segment (over 300ton) installation in long radius (~28
m) and unbalance C.G. condition.